Quality control plan for washing machine motor winding section
| Suzhou Nanxin Electric Machinery Co., LTD | |||||||||
| Parts: motor Parts Description: Motor parts processing | |||||||||
| Items | Process | Tools | Characteristic | Level | Method | Mode of handling | |||
| Object | Description | Work rules | Sample | Control Method | |||||
| Frequency | |||||||||
| Winding | Marking | Slot machine, cutting plotter | Core | Process control | B | 《退火铁芯检验内容及标准》 | 1 time/every 4 hours | Daily report of inspector and team leader | |
| Marking | Process control | B | Identification is correct | 1 time/every 4 hours | Daily report of inspector and team leader | ||||
| vernier caliper | basic size | Process control | B | 《退火铁芯检验内容及标准》 | 1 time/every 4 hours | Daily report of inspector and team leader | |||
| Work fixture | Performance | Process control | B | 《产品型号规格表》 | 1 time/every 4 hours | Daily report of inspector and team leader | |||
| Inserting winding of main wire | Winding machine, coil measuring instrument | Resistance | Process control | A | 《绕线参数表》 | The first inspection | Daily report of inspector and team leader | ||
| cylinder number | Process control | A | 《绕线参数表》 | The first inspection | Daily report of inspector and team leader | ||||
| First shaping | Shaper | First shaping | Process control | B | 《初整工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Insulating paper | / | Insulating paper | Process control | B | 《放隔相纸工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Inserting winding of sub wire | Winding machine, coil measuring instrument | Resistance | Process control | A | Resistors meet technical standards | The first inspection | Daily report of inspector and team leader | ||
| cylinder number | Process control | A | The winding number conforms to the technical standard | The first inspection | Daily report of inspector and team leader | ||||
| scraper painting | Paint scraper | scraper painting | Process control | A | 《刮漆工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Connect wire | / | Connect wire | Process control | C | 《连线工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| soldering tin | Melting aluminium furnace | soldering tin | Process control | C | 《焊锡工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Crimping | Riveting machine、micrometer | Crimping | Process control | A | 《刺破端子工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Tidy | / | Tidy | Process control | B | 《整理工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Second shaping | Shaper | Second shaping | Process control | B | 《中整工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Colligation | / | Colligation | Process control | B | 《绑扎工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Final shaping | Vernier caliper | basic size | Process control | A | 《终整工序检验指导书》 | 1 time/every 4 hours | Daily report of inspector and team leader | ||
| Visual inspection | / | Appearance | Finished product control | A | 《定子成品检验内容及方法》 | All inspection | Daily report of inspector and team leader | ||
| Comprehensive Test | General-purpose tester | Stator | Finished product control | A | 《定子测试台参数设置标准》 | All inspection | Daily report of inspector and team leader | ||
| Perpendicularity test | Work fixture | Inner hole | Finished product control | A | 《定子成品检验内容及方法》 | All inspection | Daily report of inspector and team leader | ||